Day 1 1 Jun 16 - Room prep, radiator out, non-load bearing wall removed, sink removed. Day 2 2 Jun 16 - Ceiling over-boarded, Old bathroom doorway blocked up, Floor repaired. Day 3 3 Jun 16 - 1st Fix Electrics, plaster boarding walls, ceiling prep for skimming. Day 6-8 8 to 10 Jun 16 - 2nd fix electrical, 1st fix plumbing and new radiator hanging/plumbing. Day 7 13 Jun 16 - Lutrolite Panels fitted, new floor covering fitted. Day 8 14 Jun 16 - Shower 2nd fix - mixer/enclosure. Finished Bathroom: Best hospitality ever........ Big thank you..