Day 1 6 Feb 16 - Test Dig in the rain, all good. Day 2 10 Feb 16 - Old footings out, thick concrete slab still to go. Day 4/5 12/13 Feb 16 - Excavation passed by Building Control. Concrete Strip foundations mixed on site. Day 11 22 Feb 16 - Roof windows in, roof prepared for tiles. Building Control passed roof structure and steel works. Day 12/13 23/24 Feb 16 - Facia & Soffits fitted, internal prep for plaster boarding. Roof tiling and window flashing started. Day 14 25 Feb 16 - Roof tiling finished, just the ridge and lead to complete. Rainwater soak-away hole and drain tenches dug (Thanks to John). 1st fix electrical lighting complete. Todays top tip 'Don't walk into the scaffold planks with your head'. Day 17 2 Mar 16 - 1st fix electrics finished and dining room ceiling patched ready for skimming. Day 18 4 Mar 16 - Oversite prepared, landscaping started. Window and door expected in just over a week. Day 19-21 8 - 10 Mar - Kitchen and dining room ceiling skimming, Damp Proof Membrane and floor Insulation laid. Building Control Inspection - Damp Proof Membrane/Course, 1st Fix Electrical, Pre-Plasterboarding - PASS. Day 22 11 Mar 16 - Ceiling plaster boarding, block paving. Day 23 12 Mar 16 - Roof leadwork & ridge tiles. Roof finished. Day 24 14 Mar 16 - Windows and Doors temp shuttered up while we wait for the glass to be delivered. Block paving. Day 26 / 27 18 & 23 Mar 16 - Plasterboarding and floor prep, ready for windows and concrete floor now. Completed Extension:
2 Comments
|
|