Single Storey Extension - North Hykeham

2/6/2016

2 Comments

 
Day 1
6 Feb 16 - Test Dig in the rain, all good.
Picture
Picture

Day 2
​10 Feb 16 - Old footings out, thick concrete slab still to go. 

Day 3
​11 Feb 16 - Trench ready for inspection.
Picture

Day 4/5
12/13 Feb 16 - Excavation passed by Building Control. Concrete Strip foundations mixed on site.


Picture
Day 6
15 Feb 16 - 1st Block laid then footings completed and wall blocks started.

Day 7/8
16/17 Feb 16 - Blockwork up, steels and beams in place.
Picture
Picture

Picture
Day 9
​18 Feb 16 - Blockwork completed, Roof started.

Day 10
​19 Feb 16 - Internal steel fitted.  Roof felted and ready for windows, tiles.
Picture

Day 11
22 Feb 16 - Roof windows in, roof prepared for tiles.  Building Control passed roof structure and steel works.

Day 12/13
23/24 Feb 16 - Facia & Soffits fitted, internal prep for plaster boarding.  Roof tiling and window flashing started.

Day 14
25 Feb 16 - Roof tiling finished, just the ridge and lead to complete.  Rainwater soak-away hole and drain tenches dug (Thanks to John).  1st fix electrical lighting complete.  Todays top tip 'Don't walk into the scaffold planks with your head'.

Day 15
26 Feb 16 - Rainwater soak-away completed, new path prepared, site tidy up....
Picture
Picture

Day 16
​29 Feb 16 - Roof insulated, 1st fix electrics started - Waiting for the window and door now.
Picture

Day 17
2 Mar 16 - 1st fix electrics finished and dining room ceiling patched ready for skimming.

Day 18
4 Mar 16 - Oversite prepared, landscaping started.  Window and door expected in just over a week.
Picture
Picture

Day 19-21
8 - 10 Mar - Kitchen and dining room ceiling skimming, Damp Proof Membrane and floor Insulation laid.
Building Control Inspection - Damp Proof Membrane/Course, 1st Fix Electrical, Pre-Plasterboarding - PASS.

Day 22
11 Mar 16 - Ceiling plaster boarding, block paving.

Day 23
12 Mar 16 - Roof leadwork & ridge tiles.  Roof finished.

Day 24
14 Mar 16 - Windows and Doors temp shuttered up while we wait for the glass to be delivered.  Block paving.

Day 25
16 Mar 16 - Internal plaster boarding.  Fitting date for Window and Doors in - Thu 24 Mar 16.
Picture

Day 26 / 27
​18 & 23 Mar 16 - Plasterboarding and floor prep, ready for windows and concrete floor now.

Picture
Day 28
24 Mar 16 - Window and Bi-Fold doors fitted, final prep for floor tomorrow.

Day 29
25 Mar 16 (Good Friday) - Thanks Jon & John for working.  Concrete floor mixed, laid and floated.
Picture

Picture
Day 30 - 32
30 Mar, 1 & 4 Apr 16 - Internal plaster skimming, Oak window board.

Day 33
6 Apr 16 - 2nd fix electrical prep and coving.
Picture

Picture
Day 34
7 Apr 16 - 2nd fix electrical, testing and certificate.  Tidy, woodwork sealed.  New flooring now has to wait for the concrete finished floor to dry.  External rendering also waiting for the weather to improve.  Decorating can start.
​
Picture
Picture

Completed Extension:
​
Picture
Picture
2 Comments
brillassignment review link
12/7/2019 15:36:16

I have seen many designs of ceiling on the internet but these are very different from all of them. It shows that you are highly skillful person in the field of designing. I would love to have your services in house building.

Reply
Construction blogger link
16/4/2020 07:22:25

This is a very informative article!!

Reply



Leave a Reply.

Proudly powered by Weebly
  • Home
  • About
  • Services
    • Joinery
    • Construction
    • Project Management
  • Contact
  • Gallery
  • Reviews
  • Blogs / Jobs
    • Kitchen Navenby -2022
    • Extension North Hykeham 2021
    • Extension Navenby - 2021
    • Garden Room- Navenby - 2021
    • Extension Wellingore 2020
    • Extension & Refurbishment - Navenby - 2019
    • Extension Navenby 2018
    • Extension Navenby 2017
    • Commercial Extension - GNT
    • Extension - North Hykeham - 2016