Single Storey extension - Navenby - June 2017
Day 1 - (for us)
5 June 2017 - The conservatory taken down by the new owners and the existing walls removed by the family, thank you.
Existing tiles, floor and concrete slab removed, 1st trench started.
5 June 2017 - The conservatory taken down by the new owners and the existing walls removed by the family, thank you.
Existing tiles, floor and concrete slab removed, 1st trench started.
Day 2
6 June 2017 - 3rd skip full, lots of rain and clay.
6 June 2017 - 3rd skip full, lots of rain and clay.
Day 3 - 5
7 - 9 June 2017 - Excavation, concrete strip foundation and soak-away.
7 - 9 June 2017 - Excavation, concrete strip foundation and soak-away.
Day 6
12 June 2017 - Soak-away crates and backfill, Trench blocks laid and over site preparation.
12 June 2017 - Soak-away crates and backfill, Trench blocks laid and over site preparation.
Day 7 - 10
13 - 16 June 2017 - Foundations, Radon sump installed and building inspection passed for over-site/Radon protection. Over-site poured and walls started.
13 - 16 June 2017 - Foundations, Radon sump installed and building inspection passed for over-site/Radon protection. Over-site poured and walls started.
Day 11
19 June 2017 - Scorching hot day with a 7am start to try and beat the heat - Walls going up.
19 June 2017 - Scorching hot day with a 7am start to try and beat the heat - Walls going up.
Day 12 - 13
20 - 21 June 2017 - Blockwork up to wall plate, roof on and clockwork finished.
20 - 21 June 2017 - Blockwork up to wall plate, roof on and clockwork finished.
Day 14
22 June 2017 - Roof felted, and tiled.
22 June 2017 - Roof felted, and tiled.
Day 15
23 June 2017 - Made lots of dust indoors, fixed a plumbing waste leak, oh yes and removed an internal wall.
23 June 2017 - Made lots of dust indoors, fixed a plumbing waste leak, oh yes and removed an internal wall.
Day 16
26 June 2017 - Windows and Door fitted, 1st fix electrical started, floor tiling and much more... Building Inspection - Roof / Pre Plaster boarding - Passed.
26 June 2017 - Windows and Door fitted, 1st fix electrical started, floor tiling and much more... Building Inspection - Roof / Pre Plaster boarding - Passed.
Day 17 - 18
27 - 28 June 2017 - Roof insulation, plaster boarding, window boards & 1st fix electrical completion.
27 - 28 June 2017 - Roof insulation, plaster boarding, window boards & 1st fix electrical completion.
Day 19 - 20
29 - 30 June 2017 - Grouting floor tiles, Landscaping. Plastering started.
29 - 30 June 2017 - Grouting floor tiles, Landscaping. Plastering started.
Day 21 - 21
3 - 4 July 2017 - External Cladding continues.
3 - 4 July 2017 - External Cladding continues.
5 - 6 July 17
Day 23 - 24 - Cladding, cladding and more cladding.
Day 23 - 24 - Cladding, cladding and more cladding.
10 July 2017
Day 25 - In the final week now, flooring started and stove in place just the flu to complete. Lead flashing also complete.
Day 25 - In the final week now, flooring started and stove in place just the flu to complete. Lead flashing also complete.
11 - 12 July 2017
Day 26 - 27 - Flooring in, Skirting. Almost done.
Day 26 - 27 - Flooring in, Skirting. Almost done.
2 & 4 August 2017
Day 28 - 29 - Two half days; fire completed, commissioned and roof pointed.
Day 28 - 29 - Two half days; fire completed, commissioned and roof pointed.