Single Storey extension - Navenby - June 2017


Day 1 - (for us)
5 June 2017 - The conservatory taken down by the new owners and the existing walls removed by the family, thank you.
Existing tiles, floor and concrete slab removed, 1st trench started.
Picture
Picture
Picture

Day 2 
6 June 2017 - 3rd skip full, lots of rain and clay.
Picture

Day 3 - 5
7 - 9 June 2017 - Excavation, concrete strip foundation and soak-away.
Picture
Picture

Day 6
12 June 2017 - Soak-away crates and backfill, Trench blocks laid and over site preparation.
Picture
Picture

Day 7 - 10
13 - 16 June 2017 - Foundations, Radon sump installed and building inspection passed for over-site/Radon protection.  Over-site poured and walls started.
Picture
Picture

Day 11
19 June 2017 - Scorching hot day with a 7am start to try and beat the heat - Walls going up.
Picture

Day 12 - 13
​20 - 21 June 2017 - Blockwork up to wall plate, roof on and clockwork finished.
Picture
Picture

Day 14
22 June 2017 - Roof felted, and tiled. ​
Picture

Day 15
23 June 2017 - Made lots of dust indoors, fixed a plumbing waste leak, oh yes and removed an internal wall.
Picture

Day 16
26 June 2017 - Windows and Door fitted, 1st fix electrical started, floor tiling and much more...  Building Inspection - Roof / Pre Plaster boarding - Passed.

Day 17 - 18
27 - 28 June 2017 - Roof insulation, plaster boarding, window boards & 1st fix electrical completion.

Day 19 - 20
29 - 30 June 2017 - Grouting floor tiles, Landscaping.  Plastering started.
Picture
Picture
Picture
Picture

Day 21 - 21
3 - 4 July 2017 - External Cladding continues.
Picture
Picture

5 - 6 July 17
Day 23 - 24 - Cladding, cladding and more cladding.

10 July 2017
Day 25 - In the final week now, flooring started and stove in place just the flu to complete.  Lead flashing also complete. 

11 - 12  July 2017
Day 26 - 27 - Flooring in, Skirting.  Almost done.

2 & 4 August 2017
Day 28 - 29 - Two half days; fire completed, commissioned and roof pointed.
Picture

    Tell me about your visit to this page

Submit
Proudly powered by Weebly
  • Home
  • About
  • Services
    • Joinery
    • Construction
    • Project Management
  • Contact
  • Gallery
  • Reviews
  • Blogs
    • Extension Navenby - 2021
    • Extension Wellingore 2020
    • Extension & Refurbishment - Navenby - 2019
    • Extension Navenby 2018
    • Extension Navenby 2017
    • Commercial Extension - GNT
    • Extension - North Hykeham - 2016