Extension - North Hykeham 2021

A Single story extension to the existing home starting in Spring.  The extension will create a larger open plan kitchen and new dining / lounge area.

Picture

Test digs and excavations started.
Footings dug, waste pipe installed, inspection by Building Control passed.

Foundations poured, footings built and Block and Beam Floor installed.  Kitchen alterations started as well as brick and block work.

Scaffolding in place and walls going up.  Main ridge steel in and roof construction started.  Watch out for the giant Hykeham Ants.

Roof structure completed, topping out ceremony done.  Building Control passed.

Roof felted and tiled.

Building Control Inspection, windows and Bi-Folds installed.  Floor insulation fitted and screed laid.

Plaster-boarding ceiling and walls.  Kitchen fitting started.  2nd fix Electrical and plumbing underway.

Almost done just a few tweaks and a couple of doors to sort.

Building Control Inspections - North Kesteven Building Control

Stage of Work                                                                                           Date Completed/Inspected

Excavation of Foundations                                                               13 May 21
Compacted Hardcore / Membrane / Insulation                  19 Aug 21
​
Damp Proof Course Laid                                                                    19 Aug 21
Roof                                                                                                                 12 Jul 21                                                                                                      
Electrical First Fix                                                                                   19 Aug 21
Pre-Plaster                                                                                                  19 Aug 21
Drains ready for inspection                                                               13 May 21
Drains backfilled and ready for test                                              N/A
​Completion

Proudly powered by Weebly
  • Home
  • About
  • Services
    • Joinery
    • Construction
    • Project Management
  • Contact
  • Gallery
  • Reviews
  • Blogs / Jobs
    • Kitchen Navenby -2022
    • Extension North Hykeham 2021
    • Extension Navenby - 2021
    • Garden Room- Navenby - 2021
    • Extension Wellingore 2020
    • Extension & Refurbishment - Navenby - 2019
    • Extension Navenby 2018
    • Extension Navenby 2017
    • Commercial Extension - GNT
    • Extension - North Hykeham - 2016