A Single story extension to the existing home starting in Spring. The extension will create a larger open plan kitchen and new dining / lounge area.
Test digs and excavations started.
Footings dug, waste pipe installed, inspection by Building Control passed.
Foundations poured, footings built and Block and Beam Floor installed. Kitchen alterations started as well as brick and block work.
Scaffolding in place and walls going up. Main ridge steel in and roof construction started. Watch out for the giant Hykeham Ants.
Roof structure completed, topping out ceremony done. Building Control passed.
Roof felted and tiled.
Building Control Inspection, windows and Bi-Folds installed. Floor insulation fitted and screed laid.
Plaster-boarding ceiling and walls. Kitchen fitting started. 2nd fix Electrical and plumbing underway.
Almost done just a few tweaks and a couple of doors to sort.
Building Control Inspections - North Kesteven Building Control
Stage of Work Date Completed/Inspected
Excavation of Foundations 13 May 21
Compacted Hardcore / Membrane / Insulation 19 Aug 21
Damp Proof Course Laid 19 Aug 21
Roof 12 Jul 21
Electrical First Fix 19 Aug 21
Pre-Plaster 19 Aug 21
Drains ready for inspection 13 May 21
Drains backfilled and ready for test N/A
Completion
Stage of Work Date Completed/Inspected
Excavation of Foundations 13 May 21
Compacted Hardcore / Membrane / Insulation 19 Aug 21
Damp Proof Course Laid 19 Aug 21
Roof 12 Jul 21
Electrical First Fix 19 Aug 21
Pre-Plaster 19 Aug 21
Drains ready for inspection 13 May 21
Drains backfilled and ready for test N/A
Completion